- This new concept suggests that the following will be followed before the building plan approval can be provided:
- Landowners/ developers have appointed licensed surveyor
- Landowners/ developers have deposited survey fees to the Land Surveyors Board
- Landowners/ developers have set the calculation formula for share units
- Any land-related issues or problems have been resolved at the Planning Permission stage
- Upon the issuance of licenses and sales permits, land owners/ developers may sell and begin construction.
- Within 3 months (additional 1 month appeal) after the Principal Submitting Person (PSP) confirms that the project has reached a super structure stage, the landlord/ developer must submit the Strata Proposal Plan to JUPEM.
- JUPEM will then review the plan within 1 month and if it is certified as in order, JUPEM will issue the CPSP to the landlord/ developer.
- The landlord/ developer is subsequently given a 1-month period (an additional 1 month appeal) to submit an application for a strata title to the State PTG.