The G12 (super structure) stage will only be achieved when the main structure of the building is ready. For the case of accessory parcels (vehicular parking) which does not involve structural construction, the CPSP application can still be carried out.
The landlord/ developer has to submit the Strata Proposal Plan to JUPEM within 3 months (an additional 1 month appeal) from the date of the completion of the super structure stage.
The landlord/ developer shall then submit the application for the strata title to the State PTG within 1 month (additional 1 month appeal).
Based on its interpretation, the Super Structure Stage means the stage at which the completion of the building works as certified by the relevant by-laws made under the Road, Drainage and Building Act 1974 [Act 133].
PEROLEHAN PERKHIDMATAN SEWAAN SERVER (HYPER-CONVERGE INFRASTRUCTURE) DAN PERALATAN SANDARAN SECARA SEWA MILIK UNTUK JABATAN KETUA PENGARAH TANAH DAN GALIAN PERSEKUTUAN (JKPTG T03/2024)
PERKHIDMATAN SERAH URUS BAGI PENGURUSAN FAIL TERMASUK PENYEWAAN TEMPAT, PERKHIDMATAN PENGURUSAN,MENYELENGGARA DAN MENYIMPAN REKOD DAN FAIL SERTA PERKHIDMATAN PENGESANAN SEMULA (RETRIEVAL) UNTUK JABATAN KETUA PENGARAH TANAH DAN GALIAN PERSEKUTUAN (SH02/2023)